Yingkou Power Plant is located at No.1 Mingzhu Road, Yinkou Economic Development Zone. It is bordered by Yingkou New Port on the south, adjacent to
Bohai Gulf to the west. Covering a total area of 67 hectares, Yingkou Power Plant is 63 kilometers from Yingkou city proper. Huaneng Yingkou Power Plant is a
modern thermal power plant established in June 1995 by Huaneng International Power Development Corporation and Liaoning Provincial Government. It has a total planned capacity of 4840MW. The first phase comprises 2x320MW Russia supplied super-critical coal-fired units, with commercial operation commenced
respectively in January and December of 1996. The second phase is planned to add two 600MW ultra-super critical coal-fired units. The project proposal has
already been approved by National Development and Reform Commission. Completion is scheduled for 2007.